Stormwater upgrade to start in Fairlie

From 6 June Council’s contractors will be starting to replace stormwater pipes from Denmark Street to Ayr Street in Fairlie.

From Ayr Street there will also be the installation of a short section to the helipad entrance.

The work in expected to take approximately 10 weeks.

The work will see the installation of 450mm and 375mm PVC pipe.

Our contractors will be in touch with affected residents and they will work with you if there are any short-term impacts on access to properties.

Because of the tight nature of Doon and Alloway Streets and the depth of the trench, road closures will be necessary at times.

We apologise for any inconvenience this may cause and thank you for your co-operation and patience in advance.