Over winter a large vehicle caused damage to Boundary Stream Bridge, a single lane bridge on Lilybank Road.
A bridge inspection was undertaken by Council's roading contractor Fulton Hogan to confirm the damage was not structural and the bridge was signposted to warn motorists.
|
|
Repairs were programmed to be completed once the Round Hill ski season was over to allow crews to undertake the repairs safely. Subcontractors L & L Construction undertook the repairs with High Country Earthworks managing the traffic management.
Work consisted of replacing the damaged boards and uprights on the bridge and also rebuilding the damaged concrete.